Rowad can help with power generation projects, cement factories, petrochemical utilities, electrical substations and oil & gas infrastructure.
Date: 2016 - 2017
Client: Gamesa
Duration: 14 months
Civil works and construction of 110 G80 wind turbine generators with 2 MW of nominal power and 60 m hub height on turnkey basis
Date: 2015
Client: Danieli
Duration: 8 months
Danieli is one of the largest suppliers of equipment and plants to the metal industry. After a 3-year stoppage, Danieli needed a reliable contractor to complete the project in Al Ein El Sokhna.
Date: 2011
Client: SWAG (Germany)
Duration: 10 months
Construction of 15,000 m2 windmill manufacturing facility
Date: 2012
Client: Logistica
Duration: 12 months
Construction of a 11,500 m2 specialist pharmaceuticals warehouse with 6,500 m2 air-conditioned zone and 5,000m2 cold store.
We were appointed subcontractor for the execution and completion of the Building Materials Industries Company (BMIC) cement plant located in Assiut, Egypt.