The delivered wind farm project was realized in 3 phases under 3 turnkey contracts financed by JICA, FIEM & KFW, respectively, with an overall capacity of 380 MW.
GAMESA is assigned to perform the supply & commissioning, start, and testing for 190 x 2MW SIEMENS-GAMESA G80 wind turbine generators and 60m hub height on a turnkey basis.