Owner: Saudi Electricity Company (SEC)
Contractor: Hyundai Heavy Industries
Project description: Electrical Balance of Plant
Scope of work: The PSP scope included installation of the electrical balance of plant, including but not limited to auxiliary transformer, cables, cable raceways, conduits, test equipment, DC system, and instrumentation in addition to testing, commissioning, and start-up.
Location: Saudi Arabia
Contract value: 12,450,000 USD