Engineering, procurement, construction and Commissioning of three thermal power plants with total capacity of 150 MW In CAMAMA, MORRO BENTO and HUAMBO on EPC+F basis as part of Angola emergency power plan
By using 6 units of GE- TM2500+ generation 7:
· Client: Ministry of Energy and Water (MINEA)
· Generating 150 MW
· Connected to Grid in 10 Months
· Project Value: USD 484 Million
· In operation since 2018