GRIDCo Western Region Substation & Power Transmission Infrastructure

Location: Asawinso, Juabeso, Mim

Year: 2012

Client: Ghana Grid Company (GRIDCo)

Project Operation: Optimized the power transmission infrastructure for  GRIDco through a network expansion project delivered on a turnkey basis, including the complete design, supply,  installation, and testing of a 170km, 161 kV transmission line from Aswinso to Mim through Juabeso alongside the construction of a new 161/34.5kV subtation at Juaebeso, and the expansion of an existing 161/34.5kV substation at Asawinso